环线道路改造施工组织设计(技术标).doc
《环线道路改造施工组织设计(技术标).doc》由会员分享,可在线阅读,更多相关《环线道路改造施工组织设计(技术标).doc(84页珍藏版)》请在装配图网上搜索。
Gay is now a provincial key construction project of aluminum Ltd-province with an annual output of 50,000 tons of technical innovation project of environmental protection and energy saving of electrolytic aluminum project manager. In this technological transformation projects, he has overall responsibility for the day-to-day affairs of the project. In order to ensure that southern companys control the scale of investment, strengthen field management, pay special attention to project progress, and ensure a successful operation, the overall goal. He and Engineering Department under the leadership of all the staff in the companys technical command, on the difficulties and to overcome technical difficulties in the process, work hard, have made outstanding achievements, mainly reflected in the following aspects: first, careful organization and management achieved remarkable results. Technical innovation project of the year, started and completed a series of bids and completed to date, from production engineering to put into production after nearly a year, has achieved very significant results. A project first 56 slots from dismantling the old slot just 168 days, civil engineering, installation, commissioning, guarantee engineering quality under the premise, on the production side transformation under difficult conditions, created the national industrys fastest speeds. II 32 large prebaked electrolytic cell on November 7 has been installed, marks has an annual production capacity of 50,000 tons of electrolytic aluminum production capacity of aluminum. Entire project almost 8 months earlier than planned, achieved the goal of production transformation benefits that year, created favorable conditions for aluminum through South. Second, effectively control the investment. Project is subject to a scientific approach to bidding, bidding to make savings of 20 million Yuan, in the implementation process of the project, every domestic prices of steel, cement and other building materials, the old buildings on the base encountered great difficulties in dealing with significant increase in the volume of civil engineering, but through rationalization and optimization, project control in fixed investment of 350 million Yuan. Third, environmental energy-saving effect of the project. Project investment of nearly 30 million Yuan, using large prebake technology and aluminum oxide dense phase and hyper dense phase conveying technology, fluoride and other harmful gases purification efficiency of up to 98%. Compared with Soderberg cell before the modification, power consumption can be reduced by 1500 tons of electrolytic aluminum, and project environmental protection and energy saving effect is obvious. Four are in a relatively short period of time to the normal production. After four months of efforts, a project has put into operation all the 54 240KA large cell into regular production, stable current channel conditions and all the economic indicators are good, current efficiency in October had reached 93%, is close to and reach the domestic advanced level. In the case of production half of the cell, this effect can be achieved and better level in the industry. 50,000 tons of electrolytic modification process, from preliminary study to equipment selection, cost control, project progress, quality control and coordination among the various sub-projects and various professional, technical command under the correct leadership, both from an overall perspective, emphasis on integrity, and earnestly implement the relevant laws and regulations, strictly act according to the contract. He tried to learn relevant knowledge, good style of business, operational and organizational coordination ability, project efficiency, quality and safety assurance system in place, with all units involved with the coordination and good .第1章 总体施工组织布置及规划第1节、 工程概况1、 地理位置及情况简介本工程位于武汉市三环线段内,由武汉市光谷投资建设有限公司投资建设,由中冶南方工程技术有限公司勘察、设计。本标段工程设计分为两部分1.关山立交主线改造西起庙山立交,东至光谷立交,全长1.66km,红线宽7087m。分以下几方面建设内容:1、三环线(AK13+100AK14+763.417)(1) 现状地面段道路扩容、改造。(2)现状跨线桥梁段予以保留,仅对沥青砼上面层铣刨加铺改造。2.光谷立交道路改造西起光谷立交东侧引道,东至光谷一路,全长680,红线宽50-60m.分以下几方面建设内容:1、三环线光谷立交(AK16+120AK16+800) (1) 现状地面段道路扩容、改造。(2)现状行车道沥青砼上面层铣刨加铺改造。2、 工程施工内容及主要工程数量本标段主要的施工内容为全线道路段内的排水管道工程、路基处理工程、道路工程(不含沥青路面工程)、主要工程数量如下表:序号项目名称单位数量备注1破除沥青砼面层m31102.332拆除基层m38221.613沥青稳定碎石m211704水泥稳定碎石m221995.225土工格栅m233456水泥砼路面m2656890.57 挖土方m3166318回填土方m3158219余方弃置m3335610钢筋砼管道m96911钢筋t125612回填砂石m3349013拆除排水沟m319114植草砖块料铺砌m2158015路缘石m7099616排水明沟m349017雨水管道m83518 检查井座1919砼井座1520雨、污水检查井座22第2节、 施工管理目标1、 质量目标确保本工程质量达到优良标准。分项工程合格率达到100%,单位工程优良率达到95%,工程总体达到国家施工验收规范优良标准。2、 安全目标1. 双零目标即努力实现人身死亡和重大责任事故双零目标;2. 杜绝五种事故:杜绝重大人身伤亡事故;杜绝重大施工机械设备损坏事故;杜绝重大火灾事故;杜绝重大交通事故;杜绝重大环境污染事故和重大垮塌事故;本工程施工中保证安全投入,采取积极稳妥的防范措施,遏制安全事故发生,消灭违章指挥、消灭违章操作、消灭惯性事故。3、 工期目标结合我单位市政施工经验、施工能力,优化配置人财物,合理编制施工组织设计并组织施工,确保本合同段在开工后60天内完成施工任务,自收到中标通知书后即着手项目部的组建,进行前期的施工准备工作。4、 文明施工目标文明施工目标:创建文明工区。坚持文明施工,促进现场管理和施工作业标准化、规范化的落实,树样板工程,建标准化现场,做文明职工,争创“标准化文明工地”。5、 施工管理目标精心组织,科学管理,精心施工,力创双优;安全生产,文明施工,实现“安全、优质、高效、低耗”的管理目标.6、 环保目标符合国家及地方有关环保、水保的要求,在施工中按照国家有关部委批复的环保、水保方案实施,确保工程所处的环境不受污染和通过业主验收。第3节、 施工组织及管理1、 现场组织机构框图项目经理生产经理八一路延长线工程道路工程项目经理部项目总工工程部合约部财务部质安部机料部综合办综合施工班组机修及电工班路面施工队管道施工班组防护队土方队2、 主要管理人员、机构设置职责分工1. 施工管理方法为加强本工程的施工组织管理,按期保质保量完成工程任务,项目经理部代表我司全权负责本标段工程范围内的工程施工管理和组织工作,履行合同文件中的义务和权利。2. 组织机构文字说明项目经理部设项目经理一名,总工程师一名,项目生产经理一名,下设合约部、工程部、机料部,质安部、财务部、综合办,各部室直接管理下部施工班组。3. 各部门的职责和权限:3.1.合约部:主要负责计量、签证、成本核算,效益分配等工作。3.2.工程部:主要负责生产调度,施工技术管理,施工组织设计,关键项目措施制定,生产计划及统计工作,下设测量班,负责全线道路、附属工程以及管道的测量放样、交底等。3.3.机料部:主要负责材料的采购,计划供应,管理运输、施工器具,机械设备的配置、使用等。3.4.综合办:协助业主和拆迁部门做好用地范围的拆迁征地工作,协调外部和内部人员的关系,做好后勤服务工作、做好接待文秘工作。3.5.质安部:主要负责工程质量、生产安全管理、内业资料的整理,下设试验室,负责全线需要的原材料试验及现场试验工作等。3.6.财务部:主要负责本项目的资金管理及财务分析,协助项目经理提高投资效益,确保项目资金专款专用。 第四节、施工安排施工管理、施工总体流程及安排1、 施工安排及部署 结合本标段现场实际情况,我司拟将现场划分为二个工区,光谷立交段为1工区,关山立交段为2工区,每个工区下设6个施工班组,各施工队或作业班组在项目经理部的统一指挥协调下,紧密配合,最大限度上的开展流水作业。2、 各作业班组、队职责4.1.土石方班组:主要负责全线的清表、清淤、围堰、抛填以及附属工程的基坑开挖工作,管道开挖以及回填施工等工作,并负责对路基填筑碾压成型、边坡整理工作,配合项目工程部、质安部的其他事宜,土石方班组兼管机械调度、保养维护等事宜,确保施工需要。4.2.防护队:主要负责全线的排水、支护工程工作,包括人工清理基坑、排水以及围堰工程等,同时穿插安排的工作有土工格栅的铺筑、结构物的人工回填工作。4.3.管道施工班组:负责全线雨、污水管道的安装,雨、污水检查井的砌筑。4.4.综合施工班组:负责全线其他检查井砌筑、交通、安全设施基础混凝土浇筑、钢筋的绑扎安装,路沿石以及植草砖的铺设,各施工队以外的零星工作。4.5.机修及电工班组:负责全线电力线路架设、保养、维护,机械修理、保养。4.6.路面班组:负责全线的砼路面浇筑、沥青稳定碎石,水泥稳定碎石施工以及级配碎石的施工。 附表一劳动力资源计划表附表三: 劳动力计划表 单位:人 工种按工程施工阶段投入劳动力情况6月中询6月下旬7月上询7月中询7月下旬8月上旬机械工58815105汽车司机5202020105电工344441钢筋工088000混凝土工51525222木工288220砌筑工01015202020管道安装工01530303010普工1020303035303、 施工测量组织、试验室组建中标后,我司将组织测量人员进行交接桩,交桩后立即组织导线和路基横断面复测,并及时向监理工程师递交复测书面报告,批复后即进行导线布设。导线精度需满足规范要求;其次导线必须便于测量,通视良好;再次导线点必须布置在不易扰动以及不易破坏的位置,导线点埋设一律采用标有十字线的不锈钢钢构件,混凝土护桩深度不少于50cm。沿线水准测量点布设按照200m/处,各点闭合误差在规范允许范围内。工地试验室根据工程规模配备足够数量的试验人员和仪器设备,本工地试验室拟配备如下实验的检测设备有:土工试验(击实、颗粒分析、CBR、压实度检测等);原材料检验(水泥、砂、碎石、钢材);混凝土拌和物性能检验;混凝土力学性能检验;混凝土耐久性能检验;实体混凝土质量检验;土工格栅实验检测工作则外委由相关资质的检测单位进行检测。试验室建立仪器设备档案和周期检定计划,定期校验试验设备,培训试验人员;建立完善的质量保证体系,根据施工质量管理体系文件要求编写试验室质量手册,内容包括仪器设备管理制度、样品管理制度、工作制度、程序文件、作业指导书等。采用规定的标准进行规范的试验,保证数据准确、科学,并按规定的表格清晰、完整地填写试验记录和试验报告。建立良好的档案管理体系。第4节、 施工总平面布置1、 施工总平面布置图附表二 施工总平面图2、 施工场地布置原则我们将根据工程特点及要求,精心组织,利用业主提供的区域合理布置施工现场。施工过程中尽量减少和避免对周边环境的影响,并在此前提下合理地进行各种临建、堆场、机械的布置,以最大限度地满足施工要求,成为本期施工总平面管理的中心任务。以确保本工程现场文明施工目标的实现,并为实现其他各项工程目标提供有利条件。 现场施工总平面布置图的布置充分考虑了以下几个因素:1、对现场场地情况进行了详细的考察,充分利用施工红线内征地,避开拟筑物、构筑物。2、在进行路基开挖时,要结合现场地形及场地大小合理安排开挖调配及土方运输路线。移挖做填要合理调配采用就近原则,在确保填方需求的前题下组织余土外运。3、力争做好与其他分部分项工程施工的协调和配合工作。三、施工现场布置内容一、施工用电 施工用电尽可能就近引用电源线,项目部配备多台发电机。 二、施工用水1.施工生产用水尽可能有偿利用附近水源,再采用抽水机配水车供水,主要生产点建水池或水箱,确保供水。2.施工生活用水在住宿区引进供水系统,保证生活用水的洁净。3、 施工现场通讯为保证与业主及外部的联系,项目部拟与当地电信、通讯部门联系,安装对内对外联系用电话、传真机等,同时项目部主要管理人员配对讲机若干台,以保证施工顺利。项目部将专门编制联络卡片,记上电话号码,联系方便。4、 施工生产及生活临时用房生活、办公用房拟在临建区范围附近少部分租用民房,或租用集装箱。 5、 施工围挡1.临建搭建,应与当地居民分开搭建,这样既便于施工管理,有可以尽量避免与当地居民发生冲突。2.材料仓库、维修区临建设施一律采用封闭管理,其余尽量采用封闭管理。3.如施工道路与当地交通混用,则须设置临时围挡,并设明显标识和专人看护,以免发生意外。4.施工道路与当地交通的交叉地段,设置必要围挡和专人维护疏导交通。Four outstanding works. They are derived from their own inner feelings. I also sent a student to attend the class Department speech contest, failed to get a good result, but also actively cooperate with the Department and class activities! in order to create a demonstration dorm room, our weekly class to every bedroom check, where proposed is insufficient. In order to clean up the bedroom, we use the brush brushes a bedroom again. For the class out of a force. In the event we, many projects did not get the desired results. But we understand that we tried, and in the struggle. Also has made good progress in many of the! in my class the work carried out and the results achieved, thanks to the concern and support of the Department, thanks to instructor teachers good, proper guidance, thanks to 46 students in the class will work closely together, to work together. Of course, we also have our weaknesses, needs to be further correction in their future learning and life, with a view to achieving greater results. Five declarations of good party branch branch is a fortress, a party member is a banner. Fighting in the railway engineering construction Group Headquarters Headquarters branches, a total of members 18. Role of the Xiang-GUI railway and tight South Lebanon railway, heavy, poor conditions of disadvantage, the branch closely around the construction work. Holding high the flag of our party members, unite and lead staff on the difficulties, overcome difficulties, take the zhengyou, a job well done and an engineering task, won the highly valued by leaders at all levels. Since October last year since the project began, Headquarters Branch is tightly around the center of its activities. Face South, climate is wet, sooner or later temperature larger, specific difficult, I branch from thought requirements all workers active motivated, do can long-term hard, dare fight of spirit prepared, while requirements all members lead, encouraged colleagues Zhijian each other help, each other learning business knowledge, overcome temporarily difficult, active into to engineering official starts of the prepared work in the to, play out has as a branch of fighting fortress role and members of pioneer model role. Since its start, I command under the correct leadership of the party branch in the Group and the superior party, centering on building a qualified party branches, branch of the forts and the battle to play the exemplary vanguard role of party members, actively working. In command personnel less, and task heavy of situation Xia, all members always according to party stronger, and style to are, and service better, and efficiency to high of requirements, from overall starting, better to completed has production organization, and coordination, and guarantees and the management work, in engineering progress, and quality, and benefits, and safety, aspects are made has good of results, get has owners and the Group and grass-roots units of praise. First, give full play to the exemplary role of party members. The exemplary role of party members and cadres are silent on the command, the exemplary role of party members and cadres are the best of the ideological and political education. We pay close attention to party building, requires political party members and cadres must take the lead in learning, set strict demands on themselves, .83第2章 施工方案、方法与技术措施1、 现场方案考虑到本标段工程道路拓宽工程量大,占线长,做为整个工程施工的关键线路,为缩短施工工期,本施工组织设计要求尽快组织管道施工,以便后续道路施工的顺利进行。混凝土面层质量是本工程的重点,应严格控制每道工序的质量,保证面层质量。路基填筑区严格分区分流程进行施工,分层铺筑,分层碾压、检测;管道施工在满足顶部覆土厚度的原则上,在路基填筑到合适高度时开挖施工,尽量减少管顶回填厚度,最大程度的实施机械化施工,保证路基的压实度,减少工后沉降对路面的影响。管道施工严格把握原材料关,管道接头做到不漏不渗,回填做到压实无死角,压实度满足要求,层铺及压实标准严格遵照设计及规范要求施工。 二、控制测量与施工测量 控制点的检测与中线的测设控制点复测:进场后根据交桩进行复测,并将测得结果5天内向监理工程师作书面呈报。导线检测采用城市测量规范的技术标准所规定的一级导线标准,用全站仪测角两测回,测角中误差2”,测距中误差15mm,测距相对中误差1/30000。高程检测按国家规范四等水准进行,从起点至终点逐桩检查。中线测设:根据极坐标法,采用全站仪施测。施工测量控制测量完成后,方可进行施工测量,其步骤如下:交接桩:对设计院的交桩复测无误后方可施工放线。测放中线:根据控制测量结果,测放并加密道路中线点。加密控制点:根据道路施工的环境及点位的检测分析成果,对有问题的点,尽可能不用;对影响二级测量放线精度,同时也给施工带来不便的情况,应及时加密点位。校测:在施工中应经常检测控制网及导线上的点。平面控制网测量(1)布网原则根据该标段的路线走向,拟定一级布网的施测方案,根据勘测设计的导线点靠近路线位置布设一级精度附合导线,以满足管沟、路基路面工程施工。(2)测量方案考虑到附合导线两端与已知控制点的联测,首级控制网的线路长度将达到整个线路长度以上,两端附合于四等精度的平面控制点上,并与已知点联测方位角,构成纵、横坐标和方位角条件,采用严密平差的方法进行数据处理。高程控制网测量拟定两级布网的施测方案,首级控制网建立四等电磁波测距三角高程附合网,在道路区段设四等几何水准网,当需要沉降观测时采用三等几何水准观测。水准点可敷设在导线点上或单独埋设。 管道测量管道的起点、终点及转折点称为管道的主点,管道中线定位就是将主点位置测设到地面上去,并用本桩标定。管线起点及各转折点定出以后,从线路起点开始量距,沿管道中线每隔50m钉一木桩(里程桩)。根据管线的起点和管沟的挖土中心线,一般每20m测设一点,中心线的投点容许误差为10,用灰线标明开挖边界。在测设中线应同时定出井位等附属结构的位置。每隔20m或30m槽口上设置一个坡度板。作为施工中控制管道中线和基坑开挖坡率,掌握管道设计高程的标志,坡度板必须稳定、牢固,其顶面应保质水平,用经纬仪将中心线位置测设到坡度板上,钉上中心钉,安装管道时,可在中心任务钉上悬挂锤球,确定管中线位置。以中心钉为准,放出砼垫层边线,开挖边线及沟底边线。控制槽底及管道铺设时,沟槽两帮每隔10m用施工高程点测设一对高程控制桩,标明桩号,钉高程钉画上红油漆标志作为控制辅管高程 ,为便于控制管道高程,在井室处设一对高程桩,并标明井室号,其高程下返数标明写清。2、 路基填筑4.1整体施工方案及施工工艺路基填方采用纵向水平分层填筑法施工。采用推土机运输或自卸汽车运输填料,平地机或推土机分层摊铺、分层整平。利用土方采用后退式摊铺法。重型振动压路机碾压密实,分层检查验收。路基填方施工采用“三阶段、四区段、八流程”的施工工艺组织施工:三阶段:准备阶段、施工阶段、竣工阶段;四区段:填筑区、平整区、碾压区、检测区;八流程:施工准备、基底处理、分层填筑、摊铺整平、洒水晾晒、碾压夯实、检测记录、路面整修。路基填方正式施工前28天,对各种填料进行土质试验,对符合填土要求并经监理工程师批准的土源进行取用。确定长度不小于100米(全幅路基)的试验路进行填筑试验,试验进行到能有效地使该种填料达到规定的压实度为止。试验时记录:松铺厚度、压实设备的类型、最佳组合方式、碾压遍数及碾压速度、材料的含水量、最大粒径等,试验结果报经监理工程师批准认可后,即可作为该种填料施工控制的依据,用以指导路基的施工。4.2 路基试验段施工4.2.1试验目的:为了确保路基工程质量,正确指导路基填筑施工,拟定具有代表性的路段进行填筑试验,以确定合适的压实方法,合理的机械组合及调配、压实遍数有效压实厚度和松铺系数。4.2.2、路段选择:拟在地质条件较差地段选择一处长度200m的填方地段进行试验施工,得出的试验数据以保证填土的正常施工。4.2.3机械、设备及检测仪器投入情况试验路段投入的机械设备及机械性能见下表:序号设备名称数量型号、规格、性能备 注1挖掘机2PC2002推土机1T140徐州产3振动压路机1徐工220徐州产4自卸汽车5东风载容4m3压路机的主要技术参数型号YZ220自重()20振动轮宽度()2.16振动轮直径()1.61振动频率(Hz)30激振力(KN)高336,低224.5所用试验及测量仪器见下表:序号试验/测量仪器名称规格、型号数量备注1天平5.0kg12恒温干燥箱13土壤筛60-0.074mm14粗集料筛75-4.75mm15液限塑限测定仪数显16电动击实仪17灌砂筒150183m直尺3m19全站仪DTM-352110水准仪C32II111卷尺50m212花杆3m413钢尺3m、5m各14.3、施工方法:4.3.1、试验前准备工作、基底处理施工前将清表处或者换填顶面按照设计作出相应的横坡和纵坡。试验区段基底处理的基本程序:施工前对原地面进行面积、标高测量并绘出原地面断面图并经监理工程师、业主代表签认,然后进行耕植土的开挖,开挖的深度控制必须满足设计,当与设计不符时,上报监理工程师,在设计、业主、监理到场后现场确认的数据,根据数据划分填筑的区段范围组织施工。、填方料场(取土场)确定路基工程土石方施工前,对取土场土方进行土工试验,然后对该段土进行液塑限、塑性指标、颗粒分析、含水量、密度、CBR值等试验,对经检测合格后的土允许用于施工。、路基放样路基施工前,根据恢复的路线中桩放出路基坡脚线桩,放样时按照测量的标高对应的设计宽度加宽0.5m每边,边桩处用竹桩写好填挖的高度。用(+)表示填方,用(-)表示挖方。直线段控制边桩以每20m一个,曲线则每隔10m放样一个。为保证压实机械施工中路基的有效宽度,在边桩处洒石灰或者系上颜色鲜艳的线绳,方便机械驾驶员在行驶过程中的视线诱导,考虑在边桩处埋设能控制标高的控制桩,进行施工控制。施工过程中,应保护所有标志,特别是一些原始控制点。2、试验步骤(施工流程):再次考察施工条件 -施工中边桩放样及标高测量 挖掘机取土-自卸汽车运料- 试验段卸料 -推土机推平 -人工精平- 测量松铺厚度-压路机分6、7、8遍碾压 -分别测量压实厚度、压实度-取最后有效压实厚度、压实度、松铺系数-确定最佳施工方案。以下分述上料、测高程和松铺密度、碾压及试验、路基修整等过程描述。、上料运料前对运输车辆的方量进行标定记录,根据实际填筑的面积计算好运输需要的车数。在路段填筑范围内均匀地从自卸车卸土,卸土时尽量梅花形布置,用推土机将土推开,测定土的含水量,如果含水量在最佳含水量的允许范围之内,用推土机结合人工找平,使土均匀摊平30cm厚,过湿过干的土都要采取相应晾晒、洒水措施,使土的含水量达到最佳含水量2%以内。、测量高程和松铺密度推土机初步分层推铺料层后,按布设测点用水准仪测定标高并计算横坡,如不符合要求,用推土机精平,纵横方向按设计标高保持平顺均匀,使之符合松铺厚度(30cm)及横坡(2%)的要求,用灌砂法测松铺密度。、碾压及试验采用振动压路机碾压,第遍静压,然后先两侧后中央(曲线段由内侧向外侧碾压),先慢后快,由弱至强,纵向进退式进行,碾压要达到无漏压、无死角、碾压均匀,每次碾压重叠1/3轮。为了节省试验时间,同时又能反映各压路机碾压效果,采用条带型碾压,即碾压轮中心位于测定点,在本试验段上布置若干条带,每条带各碾压两遍,用灌砂法测密度,其抽检频率按每2000m2抽检6处,用水准仪测标高,碾压遍数确定为一来一回为两遍,八遍结束后测密度,并且进行宽度、高程、横坡、中线偏位,平整度及边坡的自检验收。对每填土层压实遍数分别进行检测(从第四遍开始测量压实度,若压实遍数超过10遍,应考虑减少填土厚度),具体碾压需要的遍数以试验测出的压实度为依据,表观为压实层面无明显轮迹。、路基修整土质路面表面的整修,用机械配合人工切土或补土,并配合压路机械碾压。填方路堤边坡用人工按设计坡率1:1.5(一级)进行刷坡。填方边坡受雨水冲刷形成冲沟或坍塌缺口时,应自上而下,分层挖台阶加宽填补夯实,再按设计坡面削坡,确保边坡顺直、美观、牢固。5、整理试验结果施工结束后,在驻地监理工程师的认可下,将测量资料,相关试验资料及施工段填筑时机械配备的大小、数量、类型及挖方段挖、运机械和运输力量均应按实际情况进行统计和整理、并加以总结,得出不同机械压实不同填料(土石混合料、石方两种不同填料)的最佳含水量、适宜的松铺厚度和相应的碾压遍数、最佳的机械配备和合理的施工组织。拿出实施性指导方案上报驻地监理,申请全线段土石方开工。4.4 路基施工方法、施工工艺及技术措施4.4.1施工顺序施工顺序:施工测量场地清理排水系统基础处理(需要时)路基挖方路基填方路基防护路基修整。施工前编制阶段性作业指导书,报监理工程师批准后实施。4.4.2 施工测量 开工之前进行桩点现场恢复和固定路线。其内容包括导线、中线的复测,水准点的复测与增设,纵、横断面的测量与绘制、工程量复核等。 对所有的测量成果进行记录并整理。每段测量完成后,测量记录及成果资料由测量工程师和主管技术人员共同签字后报监理工程师核查签认。 监理工程师核准测量成果后,按图纸要求现场设置路基用地界桩和坡脚、路堑顶、截水沟、边沟、护坡道等的具体位置桩,标明其轮廓,报请监理工程师检查批准。 施工测量的精度符合公路勘测规范(JTJ061-99)的要求,施工放样符合公路路基施工技术规范(JTJ033-95)的规定。4.4.3 场地清理采用人工配合推土机或挖掘机的作业方式对路基用地范围内的房屋、道路、通讯电力设施、排水沟渠及其它建筑物和构筑物进行拆除,对正在使用的排水结构物进行改沟处理。对因拆除施工造成的坑穴进行回填、压实,并使其压实度不低于原地面密度。对路基用地范围内的树木、灌木丛等在施工前砍伐或移植。砍伐的树木堆放在路基用地之外,并妥善处理。对垃圾、有机物残渣及原地面以下至少20cm内的草皮、农作物等的根系和表土进行清除并运至弃土场。4.4.4 防水、排水系统在路基施工前,先施作临时排水及防渗设施,以保持施工场地处于良好的排水状态。临时排水设施与永久排水系统相结合,挖出的废土堆置在沟侧,予以夯实并不得阻碍水流顺畅。施工时,施工层随时保持一定的泄水横坡或纵向排水通道,做到表面不积水。3、 路堑开挖路堑开挖前,先做好顺坡坡顶截水沟,并根据土质情况作好防渗和排水工作。根据土石方调配方案和施工顺序选择最佳的开挖作业面。路堑开挖过程中从坡口线开挖,同时对开挖坡面及开挖后土体变形进行监测,确保施工安全。当路堑较深时,应横向分成几个台阶进行开挖;路堑既长又深时,应分层分段,每层先挖出一个通道,然后开挖两侧,使各层有独立的出土通道和临时防护设施。对风化破碎岩体,为保证施工中边坡的稳定和边坡防护的施工,尽可能做到开挖与边坡防护同时进行。土方开挖在进行交接桩后,即开始进行中线贯通与高程测量,做好记录,进行局部放样,绘制横断面图,确定施工边界线桩位。清理现场,拆除一切有碍施工的障碍物,做好清理地表杂物、腐殖土,砍伐树木,局部回填压实,做好场地临时排水等工作。土方的开挖及运输采用机械化作业。施工过程中及时根据测设的边线桩和设计坡度及时刷坡,并在雨季前做好天沟等配套设施,保证边坡稳定。路堑开挖接近设计标高后,预留20cm厚土层,以弥补路基压实后的沉降量。路堑及零填路段,采用20t振动压路机压实,并用灌砂法检测压实度,对于原土质不能满足要求的地段进行改良或者换填处理。4、 管道施工1管道测量施工时根据管线的起点和管沟的挖土中心线,一般每20m测设一点,中心线的投点容许误差为10,用灰线标明开挖边界。在测设中线应同时定出井位等附属结构的位置。每隔20m或30m槽口上设置一个坡度板。作为施工中控制管道中线和基坑开挖坡率,掌握管道设计高程的标志,坡度板必须稳定、牢固,其顶面应保质水平,用经纬仪将中心线位置测设到坡度板上,钉上中心钉,安装管道时,可在中心任务钉上悬挂锤球,确定管中线位置。以中心钉为准,放出砼垫层边线,开挖边线及沟底边线。控制槽底及管道铺设时,沟槽两帮每隔10m用施工高程点测设一对高程控制桩,标明桩号,钉高程钉画上红油漆标志作为控制辅管高程 ,为便于控制管道高程,在井室处设一对高程桩,并标明井室号,其高程下返数标明写清。6.2、雨水、污水管道施工本工程管道较多且分布较复杂,主要为钢带加强聚乙烯HEPE管道。施工前先严格按照设计要求完成线位控制测量工作和流水高程复核工作,以保证施工完毕后能满足排水和排污功能,考虑到管道回填沉降对路基路面的影响,拟采用分段分批开挖的施工办法,即按照各雨污水管道的流水标高,当路基填到管顶标高+50cm时进行开挖施工,以减少今后对管道两侧的回填。 工艺流程开挖人工修槽底砂石基础下管稳管、接口砌井闭水试验回填夯实。 沟槽开挖a) 开挖方式拟采用机械开挖,槽内放坡按照设计规范施工。对局部因为开挖深度较大,或者土质较差的地段,有可能影响沟槽边坡稳定和边坡安全的,采用加大放坡坡度方法和多级开挖并采取可靠的支撑或支护。开挖时沟槽底净宽按设计要求管外径加宽一定的工作宽度,坡度按照规范要求进行,保证施工安全和合理的施工工作空间。槽底20用人工清理,开挖时严格控制基底标高,防止超挖。b) 挡土板支撑为保证管道施工的质量和安全要求,在施工中对沟应采用可靠的支撑与支护。根据本工程的地质情况,沟槽开挖应进行支撑和支护,一般用撑板支撑,如遇地质不良地段或雨季施工时可考虑钢板桩支护方法;特殊地段的支护,可根据现场具体情况与监理工程师、地质部门、设计部门及业主协商,得到批准后进行施工,主要可采用锚杆和钻孔灌注桩支护等其他支护方法。根据实际情况需要加固时采用木挡土板支撑,特殊地段采用钢板桩支撑,并对支撑随时检查,以保证周围地基的稳定木材选用质地坚实、无枯节、透节、穿心裂折的松木或杉木,不宜使用杂木。支撑挖好一层支撑好一层,并严密顶紧,支撑牢固,严禁一次将土挖好后再支撑。挡土板或板桩与坑壁间的填土要分层回填压实、使之严密接触。支撑的拆除按回填顺序依次进行。多层支撑自下而上逐层拆除,拆除一层,经回填夯实后,再拆上层。拆除支撑时,注意防止附近建筑物或构筑物产生下沉和破坏。c) 施工降排水当开挖的部位高于地下水位时,一般选用集水坑降排水,集水井规格,拟采用直径或宽度0.70.8m,井底低于排水沟0.50.8m。当开挖的部位低于地下水位时, 根据地质情况,选用集水坑降水、井点降水两者相结合等措施降低地下水位。特殊地段可采用深井降水。集水坑降水:基槽集水坑排水方法时由排水沟和集水井组成。沿基槽设置排水沟并分段设置集水井,当基坑挖到地下水面时,在基坑内适当的位置挖设集水井并安装抽水泵,然后沿基坑底四周挖临时排水沟。当基坑或槽的面积较大时,可取沟深50cm左右,采用挖土机挖土时,排水沟的深度可适当增加。排水沟与集水井连接,并将排水沟内的地下水引到集水井,用抽水泵将水排除。挖土顺序从集水井、排水沟处逐渐向远处挖掘,使基坑内开挖面始终不被水浸泡。 槽基处理开挖沟槽后,应按照图纸对开挖好的沟槽复测一遍,看其平面位置和高程是否符合要求,排水沟畅通,尺寸及坡度符合施工要求,沟槽内无软泥及杂物,基面无扰动,槽壁稳固,清底合格。当软土地基、软弱土质槽基或因土质变化可能产生不均匀沉降的槽基均应按设计要求进行处理。加固处理可采用回填块石、灌砂砾石屑夯实,其处理后的复合地基承载力特征值80KN/M。 砂垫层及偎管管道基础采用150度砂砾垫层基础,偎管采用中粗砂,分层回填密实,压实度90%,分层厚度300。 管道铺设根据两检查井之间的距离,配置材料。管材长度L=设计两井长度-井内空长度。其中在端头与井连接处采用0.5的短管,中间采用长管。在基坑边侧进行连接,连接前做好管头处理。管道连接处要求干燥、清洁、无油污、无沙子。因管道为塑料管,比重较小,但比较长,管道运输到现场时可用吊车吊起后缓缓放下,这样可防止碰撞,在管道入沟槽时应采用绳子和其他合适的设备,管道不得跌落或倾倒。 管道接口:橡胶圈接口本工程钢筋砼管采用的接口形式为橡胶圈接口。橡胶圈接口安装前必须安排人员将管子插口部位倒角,还要检查胶圈质量是否合格。安装时必须将承口、胶圈等擦干净。插口插入时必须按管轴线方向插入承口,不能倾斜,否则会顶偏胶圈,致使胶圈发生不同程度的位移,产生漏水。 管道与检查井的衔接管道与检查井衔接时,可采用中介层做法:先用毛刷或棉纱将管壁的外表面清理干净,然后均匀地涂一层塑料粘接剂,紧接着在上面撒一层干燥的粗砂,固化1020 min,即形成表面粗糙的中介层。中介层的长度与检查井井壁厚度相同。6.3、检查井、雨水井的砌筑井墙材料采用M10水泥砂浆砌MU10页岩砖;检查井井基础为C10水泥混凝土;检查井井盖及雨水口材料均采用复合材料井盖。砌筑检查井、雨水井时必须砂浆饱满,砌体内外壁采用1:2防水砂浆抹面至顶,防止井室漏水。检查井与管道接口处采用半节管子,半节管子长度为1000100MM,带承口的应排在检查井的进水方向,带插口的应排在检查井的出水方向。检查井基础为C20砼基- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 环线 道路 改造 施工组织设计 技术
装配图网所有资源均是用户自行上传分享,仅供网友学习交流,未经上传用户书面授权,请勿作他用。
关于本文