1、Bangkok Mass Transit System SAPHAN-LAM LUK KA Section Section 1: SAPHAN-KHU KHOTPROJECT QUALITY PLANQuality PolicyChina Railway Construction Corporation (CRCC) being a consultant of choice is committed to quality of service it provides through the implementation of an effective Quality Management Sy

2、stem. It is our aim and policy to strive for excellence by operating towards:1. Assuring customer with reliable and quality works.2. Meeting customer requirements.3. Comply with relevant legislation and standards.4. Completing projects on time and rapid response to defects.We are committed to contin

3、ually improve the effectiveness of the qualitymanagement system.Contents1 Scope & Details (范围和细节) 82 Project Details项目简介 92.1 Project Overview项目概述 102.2 Organization Chart 组织机构图122.3 Roles and Responsibility 工作职责142.4 Distribution of Project Quality Plan项目质量计划分配 _ 202.4.1 Purpose目标 202.4.2 Scope 范围2

4、02.4.3 Responsibility职责 202.4.4 Procedure 程序_ 203 Quality Management System质量管理体系 213.1 Management Review 管理复审223.2 Auditing 审计233.2.1 External Audit外部审计 233.3 Training培训 _ _ 243.4 Revision of Project Quality Plan项目质量计划修正 253.4.1 Purpose目标 253.4.2 Scope范围 253.4.3 Responsibility职责 _ _ 253.4.4 Procedu

5、re程序 253.5 Document Control文档管理 263.5.1 Purpose目标 263.5.2 Scope 范围263.5.3 Incoming and Outgoing Document Procedure文件出入管理程序 263.5.4 Preparation, Review and Approval of Project Documents项目文件准备,复审,和批准 343.5.5 Maintenance of Master Copies of Project Documents项目文件的主要复印件的维护. _ _ 343.5.6 Project Document C

6、hanges/Revision项目文件更替/修订 343.5.7 Distribution of Project Document项目文件分配 343.6 List of Code of Practice试试规程列表 364 Planning & Scheduling 计划和安排384.1 Baseline Programme基线计划 394.2 Construction Programme 施工计划404.3 Construction Acceleration Programme优化施工计划 414.4 Procurement Schedule采购计划 424.5 Shop Drawing.

7、 Method Statement & Material Submission Schedule施工图,施工方案和材料计划 434.6 Progress Meeting进度会 444.7Progress Report 进度报告455 Procurement. 采购465,1 Sub-contractors & Suppliers Selection分包商和供应商 475.1 .1 Subcontractors Mandatory Qualification 分包商强制性资格475.1.2 Tendering Arrangement for subcontracting works 分包商工作安

8、排475.1.3 Procedure for Subcontractor! Supplier Selection 分包商程序,供应商筛选475.2 Kick Off Meeting with Sub-contractors & Suppliers分包商和供应商产品启动大会 485.3 Performance of Suppliers and Sub-contractors 供应商和分包商的执行495.3.1 General 总则495.3.2 Procedure for Assessing Performance of Suppliers & Sub-contractors 供应商和分包商的绩

9、效评估程序495.4 Purchasing of Materials & Equipment材料和设备采购 505.4,1 Material & Equipment Arrival Schedule材料和设备到达日程表 505.4.2 Material Receiving. Storage & Handling材料接收,储存和交付 505.5 Material Identification & Traceability 材料识别和追溯515.6 Material Testing 材料测试, 526 Design Management 设计管理536.1 Engineering Design T

10、eam for Temporary Work临时工程的工程设计团队 546.2 Authority Submission提交权威 546.3 Drawing Management图纸管理 546.3.1 Shop Drawings 施工图, , 546.3.2 Construction Drawings Issued by CLIENT客户发布施工图 566.3.3 As-built Drawing 竣工图587 Construction Management 施工管理597.1 Permits & Statutory Compliance 许可和官方承诺617.1 .1 General St

11、atutory Requirements一般法规要求 617.1.2 Schedule of Statutory Submission 法规提交计划表627.1 .3 Inspection & Testing Required by Statutory Authorities 法规部门的检查和测试要求627.2 Mobilization and Logistics Management 动员和物流管理637.2.1 Purpose目标, ,637.2.2 Scope 范围637.2,3 Responsibility职责 637.2.4 Procedure 程序, , 637.3 Survey

12、Control 测量控制647.3.1 Objectives 目标647.3.2 Control 01Survey Data and Records 控制测量数据和记录647.4 Request for Information (RFI)信息要求 657.5 Method Statement and Inspection & Test Plan施工方法和检查测试计划 667.5.1 Purpose目标 667.5.2 Scope 范围667.5.3 Responsibility职责 667.5.4 Procedure程序 667.5.5 Method Statement and Inspect

13、ion & Test Plans Review and Approval施工方法和检查测试计划,复审和批准7.6 Testing 01Worlls & Materials材料测试 697.7 Control of Non-conformance 不符合控制707.7.1 Purpose目标 707.7.2 Scope范围 707.7.3 Responsibility职责 707.7.4 Procedure程序 707.8 Control of Sub-contractor/Supplier供应商/分包商的控制 737.8.1 Purpose 目标737.8.2 Scope范围 737.8.3

14、Responsibility职责 737.8.4 Procedure程序 737.9 Calibration of Measuring & test Equipment 测量标定和设备测试767.9. 1 Purpose 目标767.9.2 Scope 范围167.9.3 Responsibility职责 767.9 .4 Procedure程序 167.10 Maintenance of Plant & Equipment设备维护 777.10.1 Purpose 目标777.10.2 Scope 范围777.10.3 Responsibility职责 777.10.4 Procedure程

15、序 777.11 Protection of Completed Works 成品保护787. 12 Handover 交验797.12.1 Working Area Handover Schedule工作区域移交计划 797.1 2.2 Hand over inspection 移交检查797.13 Quality Record & Archives 质量记录和归档807.13.1 Purpose 目标807.13.2 Scope范围 1107.1 3.3 Responsibility职责 807.13.4 Procedure 程序 807.14 Defect liability Perio

16、d缺陷责任期 828 Contract Administration 合同管理 838.1 Payment Claims 索赔849 Site Safety-Risk, Health .& Environment Management 现场安全风险,健康和环境管理859.1 Workplace Safety & Health Management (WSH Management)工作区域安全和健康管理 869.1.1 Risk Assessment (RA)风险评估 869.2 Environmental Control 环境管控879.2.1 Environment Impact Asses

17、sment .(EIA) Report 环评报告871 Scope & DetailsThe scope of this Project Quality Plan (PQP) incorporates the quality management of various stages and aspects in the course of the project construction including (I) Quality Management System; (ii) planning & scheduling; (iii) Procurement; (iv) Design Mana

18、gement; (v) construction management; (vi) contract administration, and (vii) site safety-risk, health & environmental control.By adopting the above quality management to various stages and aspects of the project construction, it aims at enhancing customer satisfaction and controlling the constructio

19、n process for a safe, clean and healthy working environment. This includes meeting in accordance with specified requirements and in compliance with statutory rules, legal requirement and environmental regulations related to the project.The PQP may also be used by the sub-contractors or other compani

20、es as a guideline in the event there would not be a developed PQP available within their organization.2 Project Details2.1 Project Overview2.2 Organization Chart2.3 Roles and Responsibility2.4 Distribution of Project Quality Plan2.4.1 Purpose Scope Responsibility2.4.4 Procedure2.1 Project OverviewTh

21、e Works under Contract C01 comprise the construction and completion of twelve (12) elevated station, approximately 11.4km of elevated MRT viaduct. Associated works include the construction of underpass, demolition of existing fly over and interface with one existing subway station. The rail viaduct

22、generally consists of single-track, double track and triple-track viaducts. The rail viaduct structure generally consists of piers, and pre-cast segmental post-tensioned beams spanning up to 37.5m. Bearings and expansion joints are required at the end of these continuous decks. Deep foundation eleme

23、nts forming the foundations are typically barrettes and bored piles. The casting yard will be set up for the precast structural elements such as viaduct segment, precast crossbeam shell, pre-stressed station I beam, precast parapet wall and etc. The track-form comprises a slab-track system . The Con

24、tractor shall undertake waterproofing as required prior to installation of the slab-track system by the System-wide Contractors (SWCs) and supply and install sockets in the viaduct decks for anchorage of the slab-track. 2.2 Organization ChartThe site organization chart is attached on the following p

25、age.2.3 Roles and ResponsibilityProject Director To direct overall project mission. To appoint project operation team to ensure timely completion of project. To provide advice on human resources specialized skills, technological and financial resources essential to the successful completion of works

26、. To assume ultimate responsibility for project and QAQC management and performance.Project Manager To undertake overall planning and control of the project in relation to all site management. To formulate and implement systems and policies for efficient site management. To expedite progress within

27、the constraints of available resources if the works are found lagged behind the programme of works. To carry out general management of the site that includes daily correspondences. To act as chairman of the safety committee. To attend progress meetings with CLIENT, consultant and Sub-Con. To liaise

28、with the client and the consultant and to take instructions from the client. To ensure environmental, safety and health policies are in place. To review and approve method statements and risk assessments which are prepared by professional engineer, Safety Officer and sub-contractors of special trade

29、s. To organize and control site meetings with the sub-contractors. To liaise with the sub-contractors regarding progress, quality of works, and the provision of adequate resources to carry out their respective scope of works in a timely and workmanlike manner. To ensure that the permanent works are

30、constructed in compliance with the consultants specified codes in its entity.Deputy Project Manager / Construction Manager To organize and control site meetings with the sub-contractors. To check the sufficiency of information for construction. To liaise with the client and consultant regarding disc

31、repancy of drawings and specifications. To issue Request for Information (RFI) to the client and consultant for asking the information for construction. To identify and propose effective construction methods to enhance productivity and quality of the works at reduced costs. To control material wasta

32、ges. To plan and organize dally site activities. To inform the quantity surveyor for any possible variation orders. To identify and resolve areas with reinforcement congestion. To collect and control engineering information and data from the client,consultant and in-house technical staff. To ensure

33、that risk assessments are submitted by the sub-contractors and reviewed by Safety Officer. To ensure that all temporary works on site are designed and supervised by CRCC engaged PE and the certificates of supervision are promptly issued and submitted to the client and copied to all consultants. To m

34、onitor and ensure that the Non-Conformance Report(NCR) items are promptly responded with remedial proposals for the Consultants acceptance before implementation,joint inspection after the rectification is done and finally close-out of the NCR.Site Manager/Project Engineer/Site Engineer/ Site Supervi

35、sor To plan, organize and arrange daily construction activities. To supervise the direct workers and to give instruction to the sub-contractors. To coordinate with land surveyors and sub-contractors on all setting out works. To liaise with Qualified Person (Supervision) (QPS)representative regarding

36、 standard of workmanship. To check if the works are carried out strictly in compliance with the contract specifications and requirements for the purpose of general quality control. To liaise with OP(S) representative for inspection of site works. To organize and supervise house-keeping and safety im

37、plementation. To control material wastage and unproductive deployment of workers. To report daily manpower and machinery to the Project Manager. To follow up and ensure environmental, safety and health policy compliance. To follow up and implement logistic planning set out by Planning Manager.Techni

38、cal Manager To attend technical meetings with the client and consultant. To hold technical meetings with sub-contractors and ensure all engineering provisions are in order and on schedules. To attend technical meetings with CLIENT, consultant and Sub-Con.Planning Manager To prepare the Baseline Prog

39、ramme for the work. To track and monitor the progress of works. To plan and ensure efficient use of plants, machinery, material and manpower. To prepare logistic planning of manpower, machinery and tools. To formulate the Baseline Programme. To prepare the construction programme based on the initial

40、 construction programme (Baseline Programme). Prepare fortnightly and monthly programme and issue the programmes to the staff and sub-contractors. To assist the Project Manager, Deputy Project Manager or Construction Manager in tracking and monitoring the progress of works. To attend the weekly plan

41、ning/programme meetings with CLIENT.Contract Manager To keep track of the project expenditure and to prompt the Project Manager if there is sign of potential over-budget. To undertake procurement of sub-contractors. To advise on claim issues this may significantly result in substantial time and cost

42、 implication to the project.Senior Quantity Surveyor/ Quantity Surveyor To assess claims raised by the sub-contractors. To keep record of all day work done by the sub-contractors. To prepare and submit claims to the client for verification and subsequently to follow up so that payments are received

43、promptly. To keep track of all variation works highlighted by the project team. To identify and prepare costing and quotation for variation orders. To work in tandem with the client and the consultant regarding submission of samples prior to placing order. To assist the Contract Manager in keeping t

44、rack of the project expenditure. To procure and mobilize sub-contractors and materials to meet the construction programme.Quality Assurance and Quality Control Manager To establish the quality management system for the project. To formulate the Project Quality Plan. To attend QA/QC meeting and to ad

45、vise on quality control issues.QA/QC Engineer To conduct quality control on the construction works and material by(i) arranging material tests (such as concrete cube test and steel rebar test)(ii) checking if the material/site works meet the compliance criteria;(iii) reporting to the project team fo

46、r follow-up action in case of noncompliance;and(iv) checking if the follow-up action/ rectification is taken. To assist in developing & reviewing the Inspection & Test Plan. To assist the Internal Auditor in carrying out internal audits. To check if corrective action to the non-conformance revealed

47、by internal audit is taken. To notify the project team of any defective work and non-conformance reports received from the Client or consultant, and check if remedial action is taken. To QAQC engineer should report directly to the QAQC Manager. To arrange materials for testing when necessary. Indepe

48、ndent sampling of the materials for testing shall be done by the Inspectors at frequencies specified in the CLIENT Materials & Workmanship Specification.Public Relation Officer (PRO) To liaise with person in-charge of company and public around our working area. To understand the situation of public

49、complaint, than pass the massage to Management team to solve the problem or complaint. To informed and update the work will do before any work start to public around working area.Safety Manager To advise and assist the Project Manager in implementing safety management and environmental management sy

50、stem. To prepare the Workplace Safety and Health Management System. To arrange the Safety and Health Monthly Meeting. To act as the secretary to the safety committee. To conduct site safety inspection and to promote site safety consciousness. To report findings of inspection to the Project Manager.

51、To enforce the safety rules and regulations. To update the Project Manager and the management team on any new/changes to the legal requirements. To conduct investigation of all incidents and accidents. To implement and ensure safety and health policies compliance.Risk Management Facilitator (RMF) To

52、 preparation of Civil Construction Safety Submission (CNSS) To review of Method Statements and Risk Assessments submissionSafety Supervisor To conduct site safety inspection and to promote site safety consciousness. To report findings of inspection to Safety Officer. To enforce the safety rules and

53、regulations. To ensure corrective and preventive is being taken for non-conformance onQuality Safety, Health and Environment activities and report to Safety Officer & EC Officer. To conduct Weekly Tool Box Meeting. To assemble and conduct daily morning exercise and safety briefing to workers. To fol

54、low up and ensure environmental, safety and health policies compliance.Resident Surveyors To co-ordinate with the Manager. Engineers, supervisors and project management to plan and arrange daily works. To co-ordinate with CLIENT surveyors regarding survey design matters, methods of survey, inspectio

55、n procedures and documentation. To check computations and verify survey setting out information . To prepare of survey setting out data for submission to CLIENT surveyors.To verify, maintain and monitoring of survey control markers.To compute, compile and submit survey control data to CLIENT surveyo

56、rs.To check and compile existing survey data for reference and reinstatement purposes .To check and compile as built survey for data for record purposes.To check and verify correctness of drawings before setting out.To planning and monitoring logistic requirement according to schedule and when deeme

57、d necessary.To provide data for shop drawings to CAD operator for plotting.To provide calculations to assist design section, where required.To prepare method statements for any construction phases involving survey procedures.2.4 Distribution of Project Quality Plan2.4.1 PurposeTo define the procedur

58、e for distributing the Project Quality Plans to all relevant project staff who need to be aware of the quality procedures so that no one involved in the project quality control would be missed out.2.4.2 ScopeThe Project Quality Plans have to be distributed to or made aware to the project staff invol

59、ved in the procedures of project quality control.2.4.3 ResponsibilityThe Quality Manager is responsible for the distribution of the Project Quality Plans.2.4.4 Procedurei. The Quality Manager has to distribute the Project Quality Plans to all major managerial staff including the Management Represent

60、ative,Project Director, Project Manager, Commercial Manager, Head of Safety Department, Design and Technical Manager andElectric and Mechanical Manager.ii. A controlled copy of the Project Quality Plan shall be kept at the site office and controlled by the Document Controller so that other project s

61、taff can get access to the Project Quality Plan when in need.iii. The Quality Manager shall conduct a training course to all project staff involved in the quality control procedures and inform those who do not have the controlled copy of the Project Quality Plan to approach the Document Controller t

62、o access the Project Quality Plan.iv. In the event that the Project Quality Plan is revised, the Quality Manager must distribute the amendment to all holders of the Project Quality Plan.3 Quality Management System3.1 Management Review3.2 Auditing3.2.1 External Audit3.3 Training3.4 Revision of Projec

63、t Quality Plan3.4.1 Purpose3.4.2 Scope3.4.3 Responsibility3.4.4 Procedure3.5 Document Control3.5.1 Purpose3.5.2 Scope3.5.3 Incoming and Outgoing Document Procedure3.5.4 Preparation, Review and Approval of Project Documents3.5.5 Maintenance of Master Copies of Project Documents3.5.6 Project Document Changes /Revision3.5.7 Distribution of Project Document3.6 List of Code of Practice3.1 Management ReviewProject Qual

展开阅读全文
温馨提示:
1: 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
2: 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
3.本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
5. 装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

copyright@ 2023-2025  zhuangpeitu.com 装配图网版权所有   联系电话:18123376007

备案号:ICP2024067431-1 川公网安备51140202000466号


本站为文档C2C交易模式,即用户上传的文档直接被用户下载,本站只是中间服务平台,本站所有文档下载所得的收益归上传人(含作者)所有。装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。若文档所含内容侵犯了您的版权或隐私,请立即通知装配图网,我们立即给予删除!