英文UT755建造方案书

上传人:痛*** 文档编号:78400760 上传时间:2022-04-21 格式:DOC 页数:20 大小:351KB
收藏 版权申诉 举报 下载
英文UT755建造方案书_第1页
第1页 / 共20页
英文UT755建造方案书_第2页
第2页 / 共20页
英文UT755建造方案书_第3页
第3页 / 共20页
资源描述:

《英文UT755建造方案书》由会员分享,可在线阅读,更多相关《英文UT755建造方案书(20页珍藏版)》请在装配图网上搜索。

1、BUILDING POLICY (PRELIMINARY)FORMT6015 MULTIPURPOSE FIELD SUPPLY VESSEL & PIPE CARRIERCOSCO GUANGDONG SHIPYARD CO.,LTD.DESIGN: CHECK: REVIEW: VERIFY: APPROVE: JULY, 2010 CONTENTS1 Treaty contents11.1 Owner11.2 General description11.3 Class and flag11.4 Contract award date, effective date and deliver

2、y date11.5 Others12 Main particulars and materials22.1 Dimensions22.2 Construction22.3 Main equipment and special equipment22.4 Main material29 Temporary Working Hole and Safety Access (Ref. Temporary Working hole Plan)39.1 Rout Introdution310 POLICY OF QC DEPARTMENT410.1 Quality control policy410.2

3、 Stage of cutting and process410.3 stage of component & subassembly group410.4 Stage of block subassembly410.5 Stage of block subassembly410.6 Stage of block assembly510.7 key point of quality control for outfit510.8 Electrical system installation quality control510.9 Quality assurance measure611 Th

4、e responsibilities of Material administration Department712 The principle of design department812.1 Objective of design812.2 Design Division812.3 Order phase approach812.4 Standardization912.5 Guidelines of detailed design912.6 The principles of production design912.7 Design focus control1113 Constr

5、uction management department Operating Policies1313.1 Construction target1313.2 Contral target1413.3 Construction management steps151 Treaty contents1.1 Owner1.2 General descriptionThe vessel has two main engines, 2 of Controllable pitch propellers, 4 of side thrusters. The vessel arranged as Machin

6、ery with accommodation arranged forward. The vessel built for World Wide service. Materials and equipment to be of recognized manufactors and shall satisfy the requirement of class rules accordingly.The vessel is to fullfil the general demands of the offshore industry as transport pipes, cement, equ

7、ipment and cargo to and from pipe-laying barges, drilling platforms and production platforms.Main deck to be arranged for deck cargo with an area of approx. 51 m x 13,5 m and for a load of 5t/m2.The vessel arranged with accommodation for 20 officers and crews and passengers.1.3 Class and flag Class:

8、 Det Norske Veritas (DNV)1.4 Contract award date, effective date and delivery dateEffective date Delivery date 1.5 Others If descriptions/ parameters of the equipments in the specification different from the order of equipment and technical agreement approved by owners, shipyards and designers, subj

9、ect to technical agreement.Owner furnished equipment: 2 Main particulars and materials2.1 DimensionsLength o.a.73.60 mMax draught5.83 mSailing areaWorle wideTrial speed at d=4.0 m15.0knLength b.p.p.68.30 mDeadweight d=5.83 m3150 tBreadth mld16.00 mGross Tonnage2100Depth main deck7.00 mDeck cargo cen

10、ter of gr.ty 1 m above deck1600tCargo deck, free area680m22.2 Construction2.2.1 Camber: All decks to have no sheer and camber. 600mm 625mm 600mmaft. fwd. #34 #582.2.2 Frame spacing:2.2.3 Double bottom arranged from fr. 14 - 84 and in fore thruster room.2.2.4 The vessel hull is welding combined syste

11、m in the structure, with transverse stiffent. Port side and the bottom is transverse framing. A strong box construction skeg is to be arranged at the centreline aft.The vessel has two of flap rudder.2.3 Main equipment and special equipmentMain diesel engines2sets model :C25:33L8PCD Engine output: 25

12、60 kW Engine speed.: 900rpmAux. generator2sets Generator output: (310 kVA) Voltage: 440V Frequency: 60Hz speed.: 1800rpm Enclosure: IP23Main Gear2sets Type : 600 AGHC V- KP50L Shaft generators2sets Capacity each : 1800 kVA Voltage : 440 V Frequency : 60 Hz Temperature class : F Enclosure : IP55emerg

13、ency/harbour generator1set Generator output: 150 kVA Voltage: 440V Frequency: 60HzTemperature class: F Enclosure: IP23Gearboxes for Fi-Fi pump and Fi-Fi pump2sets Capacity : approx. 1650 m3/hr. Power cons. : approx. 850 kW Pump speed : approx. 1800 r.p.m.Controllable pitch propeller2sets Make : Roll

14、s-Royce propulsion systemType : 72A/4-B-2900Number of blades : 4 each propeller, speed (MCR) : Approx 197 rpmShaft generator for Azimuth thruster Engine1set Output approx: 250 kW -310 kVA, 440 V, 60 Hz at max. rpm. Generator to be driven Aux. gen for Azimuth thruster2sets Performance: Approx. 900 kW

15、/1800 rpmDry cement tanks5sets Capacity: 2250 cb.feetForward Side thrusters2sets Type: TT1850, 590 kWAft Side thrusters2sets Type: TT1650, 590 kWSteering Gear2sets Rolls Royce independant electric-hydraulic steering gears2.4 Main materialHull steels weight: 1380 t 9 Temporary Working Hole and Safety

16、 Access (Ref. Temporary Working hole Plan)9.1 Rout IntrodutionA Access for E/R Engine room outboard staging Temporary working hole on side shell of E/R Upper platformPassageway inside of E/R Ladder gangway Upper deck Access on the upper deck Passageway inside of E/RB Access for the stern Outboard St

17、aging Temporary working hole on the sternC Access for Midship area The inclining ladder on the building berth Temporary working hole on the upper deck Staging along the bulkhead Inner bottom Outboard ladder gangway Upper deck ladder on the bulkheadD Access for the bowEngine room outboard staging Tem

18、porary working hole on side shell of E/R Upper platform Temporary working hole on the bowE Access for the superstructure Ladder gangway Upper deck Superstructure passageway10 POLICY OF QC DEPARTMENT10.1 Quality control policy1、 Intensify quality control by self-help2、 Do the process of quality contr

19、ol well3、 Intensify the supervise of technics discipline4、 Strict with the key point of quality of working procedure10.2 Stage of cutting and process Remove the burr and scraps of the free edge Precision of curve hull plating Precision of cutting plate & profile Tracing the main structure members10.

20、3 stage of component & subassembly group All of the plate of bulkhead & all of profiles to be flat by hot working Thin plate of shell & profile which being distortion to be rectify Quality control for inside of automatic submerged-arc welding seam Precision of opening for doors and windows in way of

21、 superstructure Precision of process/flat for bulkhead plating in way of superstructure10.4 Stage of block subassembly Before leaving jig, block joint seam to be flat and fairing. Shringkage and precision of cutting to be checked Precision of marking to be checked Principal dimension control and cor

22、rectness to be checked Shell plating of block concave to be checked after rectify. Angle between broadside and deck to be controlled. Anchor system: marking & installation Roughness of doors and windows opening in way of superstructure. Free edge distortion to be rectified and block to be reinforcem

23、ent. Knock-down plate to be weld temporary. Groove direction of erection joint seam after exceed been cut, out look groove quality. Process of shaft strut & casing welding to be supervised & noted. Welding process control for important blocks. Rudder at the after and foundation of main engine prefab

24、ricated and installation precision.10.5 Stage of block subassembly Height and half width control for both forward and after parts of the vessel Control the height of superstructure/ shape roughness/alignment between corrugated bulkhead which on the platform and lower the platform. Consider the pipe

25、to be press-test independence and to be vacuumed. Size and Roughness control of doors and windows opening in way of superstructure.10.6 Stage of block assembly Key block position fix on/center line/block height/level degree/width control Precision of shaft strut weld to hull structure. Block joint s

26、eam welding quality control. Block assembly cutting quality & fitting precision control, require to make sure CO2 single groove to be consistent with groove required by welding process. Axis precision control Principal dimension control of the whole vessel. Sequence of block butt-seam rectify contro

27、l.10.7 key point of quality control for outfit Tail shaft surface defect examination (before storage) Tail shaft out diameter/length/pulsation examination Tail shaft concentricity and fitting tightness examination Bearing out look examination & size measurement Forward and aft bearing and sternpost

28、defect examination Main engine/tail shaft etc. main equipment examination when arrived, and maintain control Vessel mooring control after launch Debugging quality control Tank capacity condition control Main engine bearing corrosion situation examination Rudder casing defect examination Rudder stock

29、/pintle/ bush for lower bearing precision process examination Shaft and shaft seal quality(burr clear up) Quality of all classes of valves(tightness examination, selective examination) Piping fabrication & fitting quality control Stern tube alignment, filling chock fasten quality control Tail shaft

30、installation /oil seal installation / propeller installation quality control Shafting alignment & main engine/gear box/ generator installation quality control Dock mooring test & sea trial quality control Rudder system installation quality control21 Steering gear installation quality control22 Capst

31、an position determination(alignment to chain hole) quality control10.8 Electrical system installation quality control(1) When supporting for cable had to weld to hull, should not to weld the supporting to the shell plate or metal pipe, the supporting should weld to the the object than can easy for d

32、isassembly(2) The supporting for cable that weld to hull, the seam should keep away from the structure seam on hull, the distance at least 50mm.(3) The seam of supporting that for main cable, as well as seam of supporting that for engine room/weather deck/toilet/ bathroom/ kitchen/ laundry/ refriger

33、ator, to be continuous.(4) Hole on hull for cable coaming should according with the technical requirements for cutting hole and reinforcement.Edge of hole that for Cable coaming, should keep a distance at least 20mm from the structure seam, and should not cut hole on the structure seam.(5) The end a

34、nd inside wall of Cable coaming should be fillet, so can avoid cable from damnify when pull cable.(6) The supporting for cable or the pipe for cable can not use wind-welding or electric welding to cut, should use grinding machine instead. The cutting edge should grind and fillet, to avoid cable from

35、 damnify when pull cable.(7) Inspection of lay out cable should mainly including cable direction/align/fastening and construct quality。Inspection also including : different shielded cable to fasten separated or not, truss belt fasten or not, layer quantity/shade of cable.(8) Connection of cable incl

36、uding connection of conductors and earthing of the cable, more attention must be paid to the watertightness of cable glands or collors of collors of cable box as well as the eathing of metal shell of the box.(9) Electrical equipment installation including shell protection level, equipment earthing,

37、infection to equipment from ambience.(10) Special electrical equipment such as main switchboard and switchboard for emergency, should have no pipe neighborhood. In case of can not avoid, it should be no pipe coupling below the subject switchboard.(11) Ventilation / high between upper and lower platf

38、orm/gap and corrosion prevention in battery room.(12) Antenna and voyage equipment layout, mark line at fwd and aft, base horizontal requirement.10.9 Quality assurance measure In order to make sure good construction quality, have to carry out the following technological requirements: Enhance supervi

39、sory control for precision of block fabricate and precision of block assembly. Enhance supervisory control on the spot for welding sequence of important blocks and process welding of casing. Enhance quality of cutting and fitting accuracy, to make sure CO2 single welding and submerged arc-welding gr

40、oove gap can meet the regulation. Enhance supervisory control for fabricate accuracy of big outfit. Enhance supervisory control for outfit position determination accuracy(especial for strengthen under deck). Enhance management for welding material. To weld according to relate technological process a

41、nd technical document strictly. Constitute regulation for quality control of seam, including award and penalize. High tension steel and normal steel can be distinction by obvious color. After second time of get rid of rust, to cover the seam which is going to be tightness test by adhesive tape befor

42、e spray-paint. To cut hole for outfit and equipment installation, should according to mode line. Before cutting hole on main deck or shell plating, hole size and position mark to be check and confirm first.11 The responsibilities of Material administration DepartmentThe process of material control i

43、ncludes seven steps , which are purchase order requiring scheme, purchase and order ,transportation and inspection ,storing ,delivery ,and information Feedback. To meet the supply during ship building, the material must be supplied by scheme according to the construction schedule.(1) The schedule of

44、 main equipments supply.(In another chapter)(2) The material administration must be adapted the shipbuilding tray management, hull-outfit-coating integration, as well as the progress of science and technology.(3) The steel material supply program in half year should be made with soft copies , and pu

45、rchaseg monthly.(4) Improving and Standardizing equipments supply scheme.(5) The Material Administration Department must track material and equipment delivery which ordered by owner and yard, and make sure the integrity of the material and equipment as well as its size and shape.(6) Make sure the sc

46、heme of main equipment and cast steels delivery meeting the key events.(7) The process of order, transportation ,inspecting, storing and delivery of material must be carried out strictly according to the standard of cosco-shipyard . The equipments supply should be on time as soon as possible. The ow

47、ner s supply should be arrived before blocks erection, stern casting steel, side thruster should be supplied before block assembly and main engine, generator , emergency generator should be supplied before block assembly.(8) Material and equipment purchase scheme should be made according to designin

48、g program of single ship from design department.(9) The department should collect information about material purchse including the materials quantity , quality ,delivery time , price ,service and so on to ensure the success of order.(10) The department must be sure the contract and the material supp

49、ly plan are well operated so that the ship can be built in time and the shipyard can control the key events .Coordinate the supply of different materials ,especially the supply of casting steel and large casting .The department must make sure the continuity of building as well as the continual suppl

50、y of welding consumables ,liner and other necessary materials for building.12 The principle of design department12.1 Objective of designNOITEMTHE SCHEDULE OF DESIGN DEPT IN 20101period of order equipments3 month2period of detail design2 month3Period of production designFive month, production design

51、will finish in one month after cutting start.4production design of hull structure4 month5prepare for cutting startAll of working plan and nesting plan would be finnsh before cutting start.6Integrated utilization rate at first time86%7Hull structure utilization at first time85%8Out fitting utilizatio

52、n at first time83%9Working and Nesting drawings of out fitting sectionWorking plan supplies have also started with the Hull structure10error of designingModify occurrence of total working hours compared to 5% of the production design11Rate of Error pipe designPipe and outfitting:812lofting rate of t

53、he first vessel of piping(by meter)Accommodation 85, E/R 8913Rate of pre-installed piping on block stage for the first vessel (by root)Accommodation 80, E/R 8014Designing pre-installed rate of outfitting (pieces)According to the tray system statistics15Reinforcement of outfitting and equipment83 on

54、hull structure16Pipe and cable holes on the side shell of E/R7017Rolling plan of design.Rolling plan of design, 98 of the examination completion rate12.2 Design Division In principle, in accordance with the provisions of the design department single ship design division of the table.12.3 Order phase

55、 approachEquipment order phase should be noted that several aspects:1. Control the order cost: Do not exceed the standard specifications and functional specifications, the attachment whether can be made by our-self. That cost should be taken into account.2. Note that new standard requirements for eq

56、uipment, such as oil and water separator, windlass, mooring winches, lifeboats, etc. .3. Attention to the requirements of small coating outfitting.4. Material when ordering use our optimized steel specifications, pipe specifications, standard outfit.5. New technology agreement signed by the technolo

57、gy Department standard application agreement.6. Management department should report the progress of technology agreement and confirmation of plans to other relevant department each week.and find a solution for the new problem.12.4 Standardization1. Steel, pipe materials used within the companys pref

58、erred specifications.2. All of the Outfitting, valves, piping accessories, parts procurement preference should be given national standard or part of the product standard.3. Drawing proofreaders should check the use of standardize.4. To develop and improve standards of engineering ships.12.5 Guidelin

59、es of detailed design1. The ship will be in accordance with the contract requirements and the rules in force, specifications and design requirements of the Convention.2. System layout design should pay attention to rules and device parameters to meet the changing norms and to increase the level requ

60、ired of class notation.3. In accordance with the procedures and work instructions documentation requirements to check and countersigned the drawings.4. Design supervisor should check the submittal of drawings in time, and amend as necessary and feedback.5. Drawing of approval, in order to ensure tha

61、t each implementation of approval comments, request the organizers to track the approval comments. Particularly that comment should be implemented on the project design stage, Inform the implementation of the relevant designer12.6 The principles of production design1. Emphasis on design improvements

62、 and design optimization. All the designers to maintain a clear sense of improving and cost savings.2. Analyses the quality problems of shipbuilding foregoing and improve it, set up Improvement Project Form for platform supply vessels (separate attachment) and follow up on.3. Implement the two design principle of giving priority to conduct timely and effective communication and coordination, improve efficiency.4. AM software

展开阅读全文
温馨提示:
1: 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
2: 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
3.本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
5. 装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

copyright@ 2023-2025  zhuangpeitu.com 装配图网版权所有   联系电话:18123376007

备案号:ICP2024067431-1 川公网安备51140202000466号


本站为文档C2C交易模式,即用户上传的文档直接被用户下载,本站只是中间服务平台,本站所有文档下载所得的收益归上传人(含作者)所有。装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。若文档所含内容侵犯了您的版权或隐私,请立即通知装配图网,我们立即给予删除!