BTG大联锁措施

上传人:沈*** 文档编号:45387833 上传时间:2021-12-07 格式:DOC 页数:10 大小:67.51KB
收藏 版权申诉 举报 下载
BTG大联锁措施_第1页
第1页 / 共10页
BTG大联锁措施_第2页
第2页 / 共10页
BTG大联锁措施_第3页
第3页 / 共10页
资源描述:

《BTG大联锁措施》由会员分享,可在线阅读,更多相关《BTG大联锁措施(10页珍藏版)》请在装配图网上搜索。

1、印尼BATAM TJK 265MW燃煤电站工程BTG大联锁调试措施PROCEDURE OF BTG INTERLOCK FOR INDONESIA BATAM TJK 265MW COAL-FIRED POWER PLANTDec. 2011 2011年12月ITEM NO.: Complied by:编 写:Revised by:审 核:Approved by:批 准:目 录Contents1. 安全注意事项 Safety precautions 2. 调试目的Purpose3. 仪器设备 Equipment4. 编制依据 Reference5调试范围Scope of commissioni

2、ng6. 调试前必须具备的条件 Conditions of commissioning7. 调试步骤 Process of commissioning8. 调试合格标准Acceptance of commissioning result9. 附 录 Appendices 1. 安全注意事项 Safety precautions1.1所有试验人员应严格遵守本现场的各种安全工作规定,确保试验安全可靠的进行All personnel participated in commissioning should strictly follow the commissioning procedure and

3、 site safety rules in order to ensure that tasks are performed in a safe and orderly way.1.2试验过程应统一组织统一指挥;Testing and commissioning shall be well organized and conducted under unified command.1.3在试验过程中如有危及人身及设备安全的情况,应立即停止试验;In case of any abnormal conditions leading to personal injury and equipment

4、damage, suspend testing immediately and take corrective measures.1.4试验过程中合发电机出口断路器和磁场断路器时,做好安全隔离措施,防止发电机误上电。Be sure to isolate the generator system electrically before closing generator CB and magnetic field CB to prevent inadvertent energizing the generator.2 调试目的Commissioning purpose为了指导及规范系统及设备的调

5、试工作,检验系统的性能,发现并消除可能存在的缺陷,保证系统及设备能够安全正常投入运行。Instruct and regulate the system and equipments commissioning. Verify system performance, Discover and eliminate defects might exist. Ensure the system and equipments can be put into operation safely and normally. 3仪器设备Equipment以下所有的仪器已经过校验.All the instrume

6、nts below have already calibrated.3.1 万用表: FLUKE 17BMultimeter: FLUKE 17B3.2 信号发生器:FLUKE 744Signal Source: FLUKE 7444. 编制依据Reference4.1设计图纸Design drawing 4.2制造厂家产品说明书Manufacture product document 5. 调试范围 机组BTG大联锁,即锅炉、汽轮机、发电机之间的联锁关系。Boiler-Turbine-Generator (BTG) interlock is the logic relationship be

7、tween the operations on boiler, turbine and generator.5.1锅炉主保护MFT动作信号送到ETS联跳汽轮机,汽轮机跳闸后,通过逆功率保护跳闸发电机。The signal MFT (master fuel trip) initiates the ETS to trip the turbine, after the turbine tripped, the generator will be tripped off by reverse-power protection.5.2发电机主保护动作联跳汽轮机。汽轮机跳闸后,锅炉负荷(蒸汽流量)大于30

8、%,触发锅炉MFT动作。The operation of generator main protections will intertrip the turbine, which will, in turn, initiate MFT if the boiler load(main steam flow) is greater than 30%.6. 调试前必须具备的条件Conditions of commissioning6.1机组分系统试运工作完毕,分系统试运中出现的问题已全部处理完毕;Testing and trial run of each subsystem has been fin

9、ished. All defects and abnormal conditions occurred in the trial run have been rectified. 6.2锅炉主保护(MFT)的各项试验已全部完毕,逻辑关系正确;All testing items of MFT have finished, showing the logic conditions correct.6.3锅炉各主要辅机的联锁保护试验完毕,逻辑关系正确;Testing of the interlocks and protections of boiler auxiliaries has finishe

10、d, indicating logic conditions correct.6.4汽轮机主保护的各项试验全部完毕,逻辑关系正确;Testing of all main protections of turbine has finished, showing the operation logic correct.6.5汽轮机各主要辅机的联锁保护试验完毕,逻辑关系正确;Testing of interlocks and protections of turbine main auxiliaries has finished, showing the logic correct.6.6发-变组保

11、护的各项试验全部完毕,逻辑关系正确;Testing of all protections of generator-transformer unit has been finished, showing the operation logic correct.6.7发-变组系统断路器传动试验完毕,符合设计要求。The circuit breakers (CBs) of generator-transformer unit have passed transmission test, fulfilling design requirements. 6.8现场道路畅通,通讯设施良好,照明充足。Ro

12、ads and paths in site are clear, convenient communications and sufficient lighting are available.6.9整套启动前的条件基本满足。The entire plant and support system have been made in readiness for integral unit start-up.7. 调试步骤Process of commissioning74.1试验前机组状态 Pre-testing condition of the unit 7.1.1锅炉状态:Boiler co

13、nditionl 启动送、引风机。(开关在试验位)Start ID fan and FD fan (CB in “Test” position).l 锅炉吹扫完成(信号模拟),MFT复位。Simulate completion of furnace purging. Reset MFT.l 任意模拟投入一层油枪。Simulate that oil guns at the first level are put into operation.l 在试验位合一次风机开关,模拟投入下层制粉系统。Close PA fan CB in “TEST” position and simulate to pu

14、t mill group A into operation. l 打开减温水电动门(过热器一减、二减电动门及总门,再热器事故喷水电动门、再热器微调减温水电动门及总门)。Open motorized attemperating water valves, including 1st, 2nd stage attemperators and main isolating valves of superheater, emergency spray water valve, 2nd stage attemperating valve of reheater and main isolate valv

15、es of reheater.7.1.2汽轮机状态:Turbine conditionl DEH复位。Reset DEH.l 汽轮机挂闸,主汽门开启。Latch turbine and open main steam valves.l 将汽轮机疏水阀全关。Close all turbine drain valves. l 将汽轮机抽汽逆止门及抽汽电动门全开。Open turbine extraction non-return valve and motorized valve fully. 7.1.3电气状态:Generator condition l 手动合发电机出口开关 Close gen

16、erator circuit breaker (CB) manuallyl 手动合磁场断路器 Close field breaker manually.7.2联锁试验:Testing of interlock circuits:7.2.1锅炉跳闸,联锁汽轮机跳闸,汽轮机跳闸后通过逆功率保护联跳发电机。Boiler tripping will intertrip the turbine, resulting in the generator trip by reverse-power protection. 7.2.1.1在发变组保护柜模拟逆功率值大于设定值。At generator-trans

17、former protection cabinet, simulate the value of reverse power greater than the setting value.7.2.1.2选择一项MFT保护条件,触发MFT动作。Initiate the MFT by simulating one of MFT protection conditions.7.2.1.3MFT动作,锅炉跳闸,联跳供油快关阀、回油快关阀、油角阀及吹扫阀、油枪及点火枪、一次风机、A给煤机、A磨煤机、下层制粉系统,联关减温水电动门(过热器一减、二减电动门及总门,再热器事故喷水电动门、再热器微调减温水电动门

18、及总门)。MFT action will initiate the following protection operations:1) Oil feed fast valve intertrip2) Return oil fast valve intertrip3) Oil corner valves and purging steam valves intertrip4) oil guns and ignition guns intertrip5) PA fans intertrip6) Coal feeder A and miller A intertrip7) Attemperatin

19、g water valves close (1st, 2nd and stage attemperators and main isolating valves of superheater, emergency spray water valve, 2nd stage attemperating valve of reheater and main isolate valves of reheater).7.2.1.4联锁汽轮机跳闸,主汽门关闭,联开汽轮机疏水阀,联关汽轮机抽汽逆止门及抽汽电动门。The interlock will trip the turbine by initiatin

20、g the following operations:1) The main steam stop valve will be closed.2) Turbine drain valves will be open.3) Turbine extraction non-return valve and motorized valve will be closed.7.2.1.5汽机跳闸后,汽机跳闸信号送至发变组保护柜,发电机跳闸,断路器断开。On receiving the turbine trip signal, the reverse-power protection (in the gen

21、erator-transformer protection cabinet) will trip the generator CB off.7.2.1.6试验完成后系统恢复:Restore the system on the completion of testing.锅炉复位:Restoration of boiler condition 8. 锅炉吹扫完成(信号模拟)。The furnace purging has been completed(simulate the signal).8. MFT复位。Reset MFT.汽轮机复位:Restoration of turbine cond

22、ition8. DEH复位。Reset DEH8. 汽轮机挂闸,主汽门开启。Latch turbine and open main steam valves again.7.2.1.7试验完成。Test is finished.7.2.2发电机跳闸,联锁汽轮机跳闸,汽轮机跳闸后负荷大于30%时,联锁锅炉MFT跳闸,负荷信号一般模拟300t/h(蒸汽流量)。Generator trip will trigger the turbine trip, which will directly trigger the MFT to shut down the boiler in case of load

23、ing greater than 30%, In the simulation, the load signal is generally set at 300t/h(main steam flow).7.2.2.1模拟一项发电机主保护动作,触发发电机跳闸,发电机断路器断开。 Trip generator and its CB by simulating one of faults the generator is protected against. 7.2.2.2联锁汽轮机跳闸,主汽门关闭,联开汽轮机疏水阀,联关汽轮机抽汽逆止门及抽汽电动门。The turbine will be inte

24、rtripped and the main steam valve closed, then, through interlock, all turbine drain valves opened and extraction steam non-return and motorized valves closed. 7.2.2.3汽轮机跳闸后,MFT动作,锅炉跳闸,联跳油枪、一次风机、A磨煤机、A给煤机、下层制粉系统、联关减温水电动门,再热器事故喷水电动门、再热器微调减温水电动门及总门)。After turbine tripped, the MFT will operate to shut

25、down the boiler, resulting in interlock trips of oil guns,PA fans, miller A and coal feeder A, and in closing of motorized attemperating water valves.7.2.2.4各专业恢复各系统正常,解除所有模拟、强制信号。Restore each system to normal condition and remove all simulation and forced signals.7.2.2.5试验结束。All the tests are finis

26、hed.8. 调试合格标准Acceptance of commissioning result8.1 联锁保护逻辑完善。The interlock and protection logic function is completed.8.2 BTG大联锁的I/O测点显示正确。BTG interlock I/O measuring points display right8.3 BTG大联锁的静态、动态联锁动作正确、可靠。BTG interlock captive test and dynamic test safely and smoothly.9. 附 录Appendices以下试验项目和表

27、格随着现场调试工作的进行会有必要的修改和完善。All test items and table(list) in appendices below will be changed and modifyed according to the site commissioning and temporal situation.附录Appendices附表Appendix 1 试验记录表 Testing Record Sheet 序号SL.NO内容Item试验动作关系Operation logic签名Signature 备注Remarks调试部commissioning运行部operation1锅炉主保护MFT动作Boiler shutdown by MFT1.1联跳汽轮机Intertrip of turbine & generator1.2逆功率动作联跳发电机Generator trip by reverse-power protection2发电机主保护动作Generator trip by its main protections 2.1联跳汽轮机Interlock trip of turbine2.2在锅炉负荷大于30%时直接跳锅炉;At boiler load greater than 30%, boiler MFT shall be initiated directly.

展开阅读全文
温馨提示:
1: 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
2: 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
3.本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
5. 装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

copyright@ 2023-2025  zhuangpeitu.com 装配图网版权所有   联系电话:18123376007

备案号:ICP2024067431-1 川公网安备51140202000466号


本站为文档C2C交易模式,即用户上传的文档直接被用户下载,本站只是中间服务平台,本站所有文档下载所得的收益归上传人(含作者)所有。装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。若文档所含内容侵犯了您的版权或隐私,请立即通知装配图网,我们立即给予删除!