面向负荷的生产控制与JIT生产(英文版)
《面向负荷的生产控制与JIT生产(英文版)》由会员分享,可在线阅读,更多相关《面向负荷的生产控制与JIT生产(英文版)(22页珍藏版)》请在装配图网上搜索。
1、Load-oriented manufacturing control just-in-time production for job shopsProduction Planning&Control1994 Vol.5.Wolfgang BechteHannover consultant firm1998/08/18 IntroductionA technique for job shops supporting the JIT concept -Using load-oriented order release,entry(Bechte,Kettner 1980)-Manufacturin
2、g control system is designed by Krautzig.-Implemented in many factories(Wiendahl,Bechte 19871991)Basic principles&technique for Load-oriented manufacturing control Detailed computational procedure refer to more theoretical publication written by Wiendahl(1993),Bechte(1988)content1.Objectives of load
3、-oriented manufacturing control2.Structure of load-oriented manufacturing control3.Basic concept in load-oriented manufacturing control4.Overview of a load-oriented manufacturing control system5.Example of the control system1.Objectives of load-oriented manufacturing controlReducing lead-time and WI
4、P.Keeping actual lead-time on stable lowest possible level.-Permanently In/Out put,inventory and average lead time of W/C are monitored and compared with their planned values in dynamic wayAt the same time determine Bottlenecks,short&mid-term capacity planningFurnishing realistic due-date scheduling
5、 and capacity planning2.Structure of load-oriented manufacturing controlFlow of orders for one single machineIllustrating events,a hierarchical controller levels,sectionsFigure 1.Funnel model of job shopMulti-level closed-loop control systemHigher controller level depends on theperformance of the lo
6、wer one.CompanyDISPOSITIONJob ShopMachineSalesDue DateLead timeUtilizationMfg.AssemblyReceivingShippingSupplierCustomerDisturbancesProd ScheduleLong Term CapacitiesOrder EntryMid termCapacitiesOrder releaseShort termCapacitiesOperation SequencesCapacities LoadingFigure2.Multilevel closed-loop contro
7、l system.3.Basic concept in load-oriented manufacturing control3.1 Basic relationship at a Work centerFour simple rules for regulating Input,Output,Inventory and Lead time1)constant inventory -keep In/Output the same on a avg.2)changing inventory -change input3)Average lead time -adjust In/Out ratio
8、4)Individual lead time to be even -apply FIFO rule while dispatchingAvg.lead time=Avg.Inv.Avg.OutputQueuing ordersAvg.OutputAvg.InputAvg.InventoryInputInitialInventoryAvg.Lead timeAvg.InventoryOutput curveInput curveOutputFinal InventoryControl PeriodLoadHoursTimedaysCompleted OrdersArriving OrdersF
9、igure 3.Basic relationship and throughput diagramBasic relationship at work center to plan the Input,Output,Inventory and Lead timeload limit=Planned output*(Planned lead time+Planning period)Planning period3.Basic concept in load-oriented manufacturing control3.2 Principle of Load limiting and Load
10、 conversionAdding LoadRemainingLoadLoadlimitPlannedInputActualInventoryPlannedlead timeCase Acase BTodayPlanning PeriodPlanned Inv.(Buffer)Plannedoutput(capacity)Figure4.Load limiting.In case that exceeding loads happensLoad limiting reject or prefer orders or variesRequired capacity=present load*pl
11、anning periodplanned lead time+planning periodRejectedLoadAllowedloadLoadlimitExceeding loadPresent LoadPlannedlead timeRequiredBufferRequiredcapacityFigure5.Short-term capacity planning using the load limitRequired Input CurveRequiredoutput curve.Order release should consider the work center loads
12、and capacitiesFour type of loads In case of B,D a statistical estimation is needed;Load conversion factordepreciation factor=planned output/Load limit =planning periodplanned lead time+planning periodLimiting and balance work in process by order release.Planned Inv.(I)(D)LoadlimitPlannedlead timeTod
13、ayPlanned Inv.(Buffer)Plannedoutput(capacity)(D)Planned Release(I)Ideal Released CurveFull loadConverted LoadFigure6.Derivation of conversion using the load limitA considering the available capacities of a short-term planning periods(12Week)Planned orders were scheduled backwardSelects periodically
14、those of the planned ordersStep1.Establish urgent ordersStep2.Release wotrkable ordersTime limit3.Basic concept in load-oriented manufacturing control3.3 Technique of load-oriented order release.If capacities is needed Load-oriented release require appreciate decisioncb aacabb acPlanning periodTime
15、limittodayTimeDaysDueOver dueFutureNon-UrgentOrder 4312WorkableWorkableUnworkableOmissibleABCWork centersLoadHoursLoad limitReleasedLoadRemainingLoadFigure 7.Steps of Load-oriented order release3.Basic concept in load-oriented manufacturing control3.4 Technique of load-oriented order entryThe ideas
16、of Load-oriented order entry is to avoid overloaded weeksChecks the scheduled operation dates against available capacities for a midterm planning horizon(ex 12 weeks)Realistic due dates are offered and the expected bottlenecks are indicated.Initiation capacity changes in advance if possibleOverload
17、weeks Free date.Cumulative LoadCumulative CapacityBacklogOverload WeeksUnderloadweeksPlanning horizonTodayTime weekFree DateOverloadPortion83%TotalLoad100%LoadhourFigure 8.Cumulative load and capacity of a work center.C is a critical work centerABCDEABCDEOverload WeeksTodayTime weekWorkcenterABCDEFr
18、ee DateOrder Lead TimeOperation Lead TimeRealistic Release DateRealistic Delivery DatePlanning HorizonFigure 9.Establishing a realistic delivery date of an order4.Overview of a load-oriented manufacturing control system1.Routing data2.Order data3.Item data4.Shop calendar5.Capacity data6.Transaction
19、data7.Control data:detailed tables for w/c and free definable group.ShopCalendarCapacityDataPlanningDataTransactionDataItemDataOrderDataRouteingDataPROGRAMTransactionDataPROGRAMControlDataPROGRAMShopCalendarProgramGraphsReportsPROGRAMOperationSequencingPROGRAMOrderReleasePROGRAMOrderEntryDIALOGCapac
20、itiesDIALOGOperationCompleteDIALOGOrderReleaseDIALOGOrderEntryCapacitiesEntriesCapacitiesReleaseCapacitiesSequencesGraphsReportsControlDataCONTROL SYSTEM(PC)BASIC SYSTEM(HOST)PLANNING SYSTEM(PC)Figure 10.Load-oriented manufacturing control system showing the data flow5.Example of the control system1
21、.The method of basic throughput diagrams is extended(Figure 1 with diagrams)2.Operation Throughput Element3.Planned and actual average lead time are computed for each inventory as well as average due-date dev.For release,input,output and deliveryEntryReleaseInputOutputDeliveryDispositionIndirectDire
22、ctDownstreamUpstreamOpenCycleTotal lead timeWait after operationTransport Wait before operationSetupRunInteroperation timeProcess timeDirect Load time.4.Pump-building factory characteristics products 9000 pumps Manufactured parts 26000 different itemsManpower(Job shop)180 persons Work centers 130(ma
23、inly 2 shifts)Orders 350 per week Operations 4,5 per order(Max 20)Run times 3,7 per operation Lot sizes 30 per order(1-1000)Factory began to work with the new system in 1987Improvement(compared 1991 with 1987)Inventory was twice as high in 1987Most delivery higher than in 1987Cycle lead time(release
24、 delivery)were cut from almost 8weeks to 5weeksDue-date deviations 4.5 to 1 week(lateness)Total lead time(entrydelivery)14weeks to 9 weeksConclusionLoad-oriented manufacturing control system enables the factory 1.Reducing lead time and inventories 2.Keeping actual lead time on a planned level 3.Meeting the planned due dates 4.Maintain an appropriate work-center utilizationresults in safer scheduling foundation for JIT production演讲完毕,谢谢观看!
- 温馨提示:
1: 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
2: 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
3.本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
5. 装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。