1、Mixing(配料) Mix solvent and bound separately with positive and negative active materials. Make into positive and negative pasty materials after stirring at high speed till uniformity. Coating(涂布)Now, we are in coating line. We use back reverse coating. This is the slurry-mixing tank. The anode(Cathod

2、e) slurry is introduced to the coating header by pneumaticity from the mixing tank. The slurry is coated uniformly on the copper foil, then the solvent is evaporated in this oven. (下面旳根据状况而定)There are four temperature zones, they are independently controlled. Zone one sets at 55 degree C, zone two s

3、ets at 65 degree C, zone three sets at 80 degree C, zone four sets at 60 degree C. The speed of coating is 4 meters per minute.You see the slurry is dried. The electrode is wound to be a big roll and put into the oven. The time is more than 2 hours and temperature is set at 60 degree C.Throughout th

4、e coating, we use micrometer to measure the electrode thickness per about 15 minutes. We do this in order to keep the best consistency of the electrode.Vocabulary: coating line 涂布车间 back reverse coating 辊涂 coating header 涂布机头Al/copper foil 铝/铜箔 degree C 摄氏度 temperature zones 温区wind to be a(big)roll

5、收卷 evenly/uniformly 均匀 oven 烘箱evaporate 蒸发 electrode 极片Cutting Cut a roll of positive and negative sheet into smaller sheets according to battery specification and punching request.PressingPress the above positive and negative sheets till they become flat.PunchingPunching sheets into electrodes acco

6、rding to battery specification,ElectrodeAfter coating we compress the electrode with this cylindering machine at about 7meters per minute. Before compress we clean the electrode with vacuum and brush to eliminate any particles. Then the compressed electrode is wound to a big roll. We use micrometer

7、to measure the compressed electrode thickness every 10 minutes. After compressing we cut the web into large pieces. We tape the cathode edge to prevent any possible internal short. The large electrode with edge taped is slit into smaller pieces. This is ultrasonic process that aluminum tabs are weld

8、ed onto cathodes using ultrasonic weld machine. We tape the weld section to prevent any possible internal short. And finally, we clean the finished electrodes with vacuum and brush. Vocabulary:cylindering 柱形辊压 vacuum 真空 particle 颗粒wound 旋紧卷绕 micrometer 千分尺 internal short 内部短路slit 分切 ultrasonic 超声波 w

9、eld 焊接Anode making In anode making process, we cut the material into certain length strips. At the mean time, we put a small piece of insulation tape to the tab in order to prevent any possible internal short. Then the prepared nickel tab is riveted on anode and pat plain. We also tape the rivet sec

10、tion to prevent any possible internal short. And finally, we clean the finished electrodes with vacuum and brush.Jelly roll This is Jelly roll, a manual winding process. In the course of Jelly roll, firstly, we place the separator in between central pins, press the foot switch to turn central pins a

11、bout 120 degrees. Secondly, place the anode to the edge of central pins, and turn central pins about 180 degrees. Lastly, place the cathode to the edge of central pins. During the winding process, we apply tension by pressing the electrodes and the separator. We put the termination tape at the end.

12、After Jelly roll, we check the short circuit, then form the Jelly roll by pressing, so that it is easier to insert the Jelly roll into the can. Control points:1. When winding to the end of the anode, covering the anode completely by the separator.2. In the whole process, it is the most important poi

13、nts to ensure the best alignment among the cathode, the anode and the separator for the Jelly roll. The separator has to cover the anode and the cathode, and the anode has to cover the cathode completely. These points are mainly checked before short checking. Vocabulary: Jelly roll 卷绕 Manual 手工旳 Sep

14、arator 隔阂纸central pin 卷针 foot switch 脚踏开关 anode 负极片cathode 正极片 termination tape 尾端胶纸 short circuit 短路alignment 整洁 Taping & insertingPut the tape on the two side of J/R, To prevent J/R being hurt in the insertion process.Put a piece of tape between cathode tab and J/R .Because anode electrode is wide

15、r than cathode electrode. Put the bottom tape.Insert the finished J/R into the can manually and then short circuit check by multi-meter.Spot welding Ni tab to cap.Ultrasonic welding the Al tab to cap using ultrasonic weld.We have the second spot welding to ensure the best contact between the tab and

16、 cap.Apply top insulator, to prevent Ni tab contacting with can.Final J/R insertion by the centrifuge.Cap positioning by hand. Then check the cap in the suitable position, or the defects is put into red bin ,Finally , short circuit check again to ensure that there be no internal short J/R flowing to

17、 next line. Vocabulary:J/R 极芯 tape 胶纸 electrode 极片 multi-meter 万用表 Spot welding 点焊Ni tab 极耳 Ultrasonic weld 超焊 Insulator 隔圈 centrifuge machine 甩壳机defect 次品 red bin 红盒Laser welding This is the Laser welding room! The first process is welding for the aluminum cap, specially connect the rivet with the

18、weld plate to prevent the cell impedance excursion. The second process is the Laser seam welding. In the process, it must ensure the intensity and airproof characters of the weld.After the cell is welded, we would perform the leak checking, the short circuit checking and the weighing checking. Vocab

19、ulary:Laser welding room 激光焊接车间 Cap 盖板 Rivet 铆钉 Plate 镍片impedance excursion 内阻漂移 intensity 强度 leak checking 检漏short circuit checking 测短路 weighing checking 称重 Oven drying electrolyte filling and storingThis is the process of cells oven drying at 80 for more than 12 hours under vacuum. After oven dryi

20、ng, the cells are transferred to the process of electrolyte filling through this channel. The electrolyte filling performs in dry room. The electrolyte is injected in two times so that it can be filled easily and sufficiently. When filling, vacuum first, then inject electrolyte. After that, we repea

21、t vacuum and vent to room pressure several times. Finally the cell is put off at room pressure, then weigh the cell in order to check the amount of electrolyte. After weighing, we seal with tape onto the filling port to prevent the cells absorbing water during storing. We store the filled cells for

22、24 hours at room temperature so that the electrolyte can be saturated sufficiently by the anodes and cathodes. Vocabulary: oven drying 烘烤 vacuum 真空 electrolyte filling 注液 electrolyte 电解液room pressure 大气压 filling port 注液孔 storing 陈化 saturated 浸润anode 正极 cathode 负极 Pre-charge and ball seal At first, w

23、e place a piece of absorb cotton above the filling port to absorb the excess electrolyte. This is the first process.The second process is performing a pre-charge at 0.1C rate for 390 minutes. After the pre-charge, we take a voltage checking to the cell at once. If the voltage is lower than the stand

24、ard, it needs to be re-charged. The fourth process is the ball seal. we must complete this process in 15 minutes.First, put the steel ball in the right place. Then, give pressure to it so that the steel ball can fill the filling port.In the whole process, we must make sure that the temperature and h

25、umidity are in the regular range. Finally, the process is cleaning to eliminate the electrolyte on the cell surface with acetone solvent. Vocabulary:filling port 注液孔 electrolyte 电解液 pre-charge 预先充电 ball seal 封口 voltage checking 量电压 regular range 合格范畴 eliminate 消除 acetone solvent 丙酮溶剂 Aging and Forma

26、tion This is the aging room. We age cells at 3540 Degree C for 7 days. The temperature is controlled by two heating instruments which are set at 38 Degree C. Then we transfer cells to the testing workshop. First, we check the voltage of cells with multi-meters. According to voltage, we divide the ce

27、lls into acceptables and defects. Formation is done at 1.0 Capacity rate for 140 minutes to 4.2 Voltage. After that, check thickness and impedance. At last, we transfer the acceptables to the storehouse. Vocabulary:aging room 老化房 heating instrument 加热器 testing workshop 检测车间acceptables 良品 defects 次品

28、formation 化成 thickness 尺寸,厚度impedance 内阻 storehouse 仓库标记牌内容(中文) 英文 1 正极球磨 Cathode Ball Mill Mixing 2 负极球磨 Anode Ball Mill Mixing 3 正极混浆 Cathode Slurry Mixing 4 负极混浆 Anode Slurry Mixing 5 正极涂布 Cathode Coating 6 负极涂布 Anode Coating 7 极片烘烤 Electrode Drying 8 正极压片 Cathode Compress 9 负极压片 Anode Compress 1

29、0 正极分大片 Cathode Cutting 11 正极分小片 Cathode Slitting 12 负极分大片 Anode Cutting 13 负极分小片 Anode Slitting 14 切镍带 Anode Tab Cutting 15 极耳铆接 Anode Riveting 16 极耳贴胶纸 Anode Tab Taping 17 大片贴胶纸 Cathode Edge Taping 18 刷片 Electrode Brushing 19 极耳超焊 #1 Cathode Tab Welding #1装配车间英语极片烘烤 Electrode Drying Area 裁隔阂纸 Sepa

30、rator Cutting壳体贴膜 Out-film Apply 超焊铝镍带Cathode Tab Welding贴内壁胶纸Inner Insulation Taping 卷绕Jelly Roll Winding检查#1 Checking Station#1 整形Jelly Roll Forming 贴侧面胶纸J/R Side Taping 贴上端胶纸J/R Top Taping贴底部胶纸J/R Bottom Taping 装壳Jelly Roll Insertion点焊负极Anode Tab Welding 剪正极耳Cathode Tab Cutting超焊正极耳#2 Cathode Tab Welding #2 二次点焊Spot Welding套隔圈Insulator Insertion 甩壳Final J/R Insertion卡盖板Cap Installation 检查#2 Checking Station #2点焊盖板Cap PreWelding 激光焊接Laser Seam welding整形Forming 检查漏气Leak Checking短路测试Hipot 称重分档Weighing Sorting

展开阅读全文
温馨提示:
1: 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
2: 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
3.本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
5. 装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。
关于我们 - 网站声明 - 网站地图 - 资源地图 - 友情链接 - 网站客服 - 联系我们

copyright@ 2023-2025  zhuangpeitu.com 装配图网版权所有   联系电话:18123376007

备案号:ICP2024067431-1 川公网安备51140202000466号


本站为文档C2C交易模式,即用户上传的文档直接被用户下载,本站只是中间服务平台,本站所有文档下载所得的收益归上传人(含作者)所有。装配图网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。若文档所含内容侵犯了您的版权或隐私,请立即通知装配图网,我们立即给予删除!